  • Vinh Tan IV Extension 600MW x 1 Units
    Period Aug. 2015 - Oct. 2016
    Client EVN GENCO 3
    Location Binh Thuan, Vietnam
    Boiler Type Super-Critical Once Through, Two Pass Type
  • Obra-C 660MW x 1 Unit
    Period Jul. 2017 - Oct.2018
    Client India
    Location Uttar Pradesh, India
    Boiler Type Super-Critical Once Through, Two Pass Type
  • Sodegaura 75MW x 1 Unit
    Period Nov. 2019 - Dec. 2020
    Client Japan
    Location Chiba, Japan
    Boiler Type Biomass
  • Fushimi Kankyo Hozen 22MW x 1 Unit
    Period Aug. 2020 - May 2021
    Client Mitsubishi Heavy Industries Environmental & Chemic
    Location Japan
    Boiler Type Industry boiler
  • Palu-3 CFB 50MW x 2 Units
    Period Mar. 2021 - Mar. 2022
    Client WIKA
    Location Indonesia
    Boiler Type Biomass
  • Vung Ang 2 TPP 600MW x 2 Units
    Period Jun. 2020 - Dec. 2023
    Client VAPCO
    Location Ha Tinh, Vietnam
    Boiler Type Super-Critical Once Through Boiler
  • Jawa 9 & 10 1,000MW x 2 Units
    Period 2021 - 2023
    Client PT LPL
    Location Banten, Indonesia
    Boiler Type Super-Critical Once Through Boilerr
  • Sakaiminato 28.11 MW
    Period 2023 ~
    Client Mitsubishi Heavy Industries Power IDS
    Location Tottori, Japan
    Boiler Type Biomass